NextDC delays Melbourne data centre expansion due to power pole protests and regulatory hurdles
Consensus Summary
NextDC, Australia’s largest data centre operator, has faced a major setback in its expansion plans for the West Footscray facility after community opposition and regulatory delays forced it to revise its financial forecasts and defer critical power upgrades. The company announced on Wednesday that its net revenue for the current financial year would fall to between $475 million and $500 million, down from an earlier projection of $615 million to $640 million. The delays, attributed to protests over the installation of 15-metre to 22-metre-high power poles and broader community resistance, have pushed back the next grid supply to the M3 data centre until 2028, according to ABC and Guardian reports. Jemena, the energy supplier, has suspended parts of the network works required to increase power capacity, leaving the project in limbo. The company’s share price plummeted by 40 per cent following the announcement, reflecting investor concerns over the prolonged uncertainty.
The controversy stems from NextDC’s plans to double the size of its West Footscray data centre, expanding it from 5 hectares to 10 hectares and increasing its power capacity from 60 megawatts to 225MW. The facility, located just 10 kilometres west of Melbourne’s CBD and 15 metres from residential homes, has long faced opposition from locals over noise, pollution, and the visual impact of towering power infrastructure. The Age notes that the power poles, designed to carry 66,000 volts—160 times the voltage of standard residential poles—have become a flashpoint, with residents in Yarraville blocking construction crews last month. The Guardian reports that Jemena halted work due to safety concerns, lack of access, and council non-approval of the poles, which rise as high as 22 metres in some areas. The delays have also triggered broader questions about Victoria’s ability to support the rapid growth of AI-driven data centres without adequate grid infrastructure.
Key figures involved in the dispute include NextDC’s CEO Craig Scroggie, who acknowledged the challenges in a call with investors, and local resident Sean Brown, a member of the Citizens of Tottenham group, who has led opposition to the project. Scroggie expressed disappointment over the technical delays but remained confident in the project’s eventual approval, citing compliance with planning rules and the need for greater community consultation. Brown, however, framed the issue as a fight for local liveability, stating that the community’s concerns had not been adequately addressed. The Age highlights political pressure on Premier Ben Carroll ahead of the November state election, with local Labor MPs calling for a pause on new developments. Meanwhile, the Victorian government has introduced new regulations, including 150-metre buffer zones between data centres and homes, in response to growing public backlash.
While the three outlets largely agree on the core issues—community opposition, power supply delays, and financial revisions—they differ in some details. The ABC emphasizes the financial impact on NextDC, including a $1.3 billion capital expenditure outlay and the company’s $7 billion valuation, while The Age and Guardian focus more on the broader infrastructure challenges and political implications. The Age also notes that NextDC’s share price had already fallen 44 per cent since June, suggesting pre-existing investor concerns. Additionally, there are discrepancies in the height of the power poles, with the ABC citing 15 metres and The Age and Guardian mentioning up to 22 metres in some locations. The timing of the protests is also slightly varied, with the ABC referencing September and the other outlets referring to last month.
The unresolved issues center on the timing of the power supply resolution and the Victorian government’s planning approval for the expansion. NextDC expects the earliest possible approval for the project’s later stages to be February 2027, but the Guardian attributes this delay to the upcoming state election and the government entering caretaker mode. The Age suggests that the broader challenge extends beyond NextDC’s project, as Victoria’s rapid push to attract AI infrastructure has outpaced grid planning. Residents, meanwhile, remain firm in their demands for remediation and compensation, with Brown warning that the new government after the election will face continued pressure. The outcome of the November state election and the government’s response to community concerns will likely determine the future of the West Footscray data centre and similar projects across Victoria.
✓ Verified by 2+ sources
Key details reported by multiple sources:
- NextDC operates 17 operational data centres in Australia, with another nine in development or planning stages.
- The West Footscray data centre is located 10 kilometres west of Melbourne’s CBD and spans 41,000 square metres.
- NextDC’s net revenue guidance for the current financial year was revised down to $475 million to $500 million, from $615 million to $640 million.
- The company’s operating profitability was revised down to $245 million to $265 million, from $385 million to $410 million.
- NextDC’s share price dropped by 40 per cent following the announcement of delays.
- The power supply delay for the West Footscray data centre is now expected until 2028, deferring contracted capacity delivery.
- Jemena, the energy supplier, has suspended parts of the network works required for the next increase in grid supply to the M3 data centre.
- The West Footscray data centre is located 15 metres from homes, sparking community opposition over noise and pollution concerns.
- The Victorian government’s planning decision on the expansion of the West Footscray data centre is delayed until after the 28 November state election.
- NextDC’s expansion plans include doubling the size of the M3 site to 10 hectares, increasing capacity from 60 megawatts to 225MW.
- The power poles required for the data centre carry 66,000 volts, approximately 160 times the voltage of previous poles.
- NextDC applied to Victoria’s planning minister in March under the Development Facilitation Program to expand the West Footscray centre.
- The Victorian government announced new regulations requiring 150-metre buffer zones between data centres and homes/schools, and mandating renewable energy use.
Points of Difference
Details reported by only one source:
- NextDC’s planned capital expenditure outlay is $1.3 billion, with the West Footscray centre’s capacity upgraded from 200MW to 225MW.
- NextDC’s stock trading was suspended on Monday due to the need for a market update on power supply delays.
- Citizens of Tottenham, a local residents group, called for remediation and financial compensation for impacted residents, including voluntary buybacks.
- The Victorian government’s fast-track Development Facilitation Program was used to approve NextDC’s Port Melbourne facility in 75 days early this year.
- NextDC’s total valuation is close to $7 billion.
- The power poles in some locations rise to 22 metres, or seven storeys high, according to Maribyrnong City Council.
- NextDC’s share price had fallen 44 per cent since June to $9.18 at Friday’s market close before the trading halt.
- The Victorian government’s rapid push to attract AI data centres has outpaced grid infrastructure planning, creating broader challenges.
- Premier Ben Carroll introduced new regulations in June requiring developers to supply their own renewable energy and use recycled water.
- Local Labor MP Katie Hall has called for a pause on data centre developments ahead of the state election.
- NextDC’s share price dropped from over $9 a share to $5.69 a share after exiting the trading halt on Wednesday.
- Jemena suspended works due to safety concerns, lack of access from community opposition, and council non-approval of 22-metre-high power poles.
- NextDC expects the earliest approval for the expansion to be February 2027, citing the upcoming 28 November state election and caretaker mode.
- The application for the expansion has been with the Victorian government since February 2026.
- NextDC is exploring alternate locations for power poles through industrial zones or underground connections.
Where the reporting differs
Details that conflict, or appear in only some outlets:
- The ABC states the power poles are 15-metre-high, while The Age and Guardian describe them as 22 metres high in some locations.
- The ABC mentions a 15-metre-high power pole installation halted in September, while The Age and Guardian refer to the protest occurring last month.
- The Guardian states the power poles are up from 11 metres today, while The Age and ABC do not mention the previous height.
- The ABC and Guardian mention the power supply delay is now expected until 2028, but The Age does not specify a year for the delay.
- The ABC states the power poles carry 66,000 volts, while The Age mentions 400 volts for typical residential poles but does not contradict the 66,000 volts figure.
Source Articles
Tech giant shares plunge 40pc after delays to Melbourne data centre
Community opposition to one of Victoria's largest data centres has seen the value of shares in NextDC plummet.
Power pole protest delays data centre giant’s flagship Melbourne project
Listed data-centre operator NextDC has requested a trading halt on the ASX, after it said power supply delays would hit its flagship West Footscray facility.
Australia’s largest datacentre operator NextDC’s shares dive as Melbourne expansion delayed
NextDC tells investors plans to double the size of its west Melbourne datacentre have hit obstacle after community objects to 22 metres-high power poles Get our breaking news email , free app or daily news podcast Australia’s largest datacentre operator has been forced to delay the controversial expansion of its M3 site in Melbourne’s west amid a pause in construction of new 22m power poles following community protest. On Wednesday, NextDC told the Australian Stock Exchange that delays to electr
More Technology stories
Alleged attack on Australian MP Helen Haines by Brendan Nugent in Wangaratta
New Zealand Silver Ferns dominate Australia Diamonds in Constellation Cup series
Prince Harry seeks reconciliation with British royal family after years of estrangement
Independent review exposes NT child protection failures in Kumanjayi Little Baby case
Sally Rooney withdraws books from UK over Palestine Action support and terrorism laws
Expedition to Nikumaroro Island searches for Amelia Earhart’s lost plane wreckage
Latest cross-verified stories
Russell Brand faces trial for multiple sexual assault allegations spanning 1999–2009
Mark Allen considers retiring from snooker after emotional Northern Ireland Open defeat
Nick Blakey's trade from Sydney Swans to North Melbourne amid Pullman Hotel scandal
PNG Chiefs unveil logo and jersey amid legal dispute with NZ Rugby
Australian youth radicalisation and school shooting plot linked to online extremism
Dog attacks in Brisbane park linked to a death; homelessness crisis highlighted
Browse all stories from October 2026 in the archive.