Melbourne Airport rail link project update and stage two construction plans
Consensus Summary
The Victorian and federal Labor governments have announced a major acceleration of the Melbourne Airport rail link, with stage two of the project set to begin construction in 2028 and the Keilor East station completed by 2031. The new 7.4-kilometre rail line will connect Albion to Keilor East, including a 500-metre bridge over the Maribyrnong River, and will link directly to the Metro Tunnel. Site investigations and procurement will start within weeks, with community engagement and early designs beginning next year, as reported by ABC, 7NEWS, and THEAGE. The project, a $12 billion joint commitment, aims to provide direct rail access to Melbourne Airport, addressing decades of delays and disputes over station location and construction methods.
The Melbourne Airport rail link has been in discussion since the 1960s, with repeated setbacks and shifting timelines. Disputes over whether the station should be built underground or above ground stalled progress in 2023, leading to a federal infrastructure review. Melbourne Airport ultimately agreed to an above-ground station in July 2024, allowing the project to move forward. ABC notes that the community has waited 62 years for the Keilor East station, while THEAGE highlights that the Andrews government initially pursued a connection via Sunshine, diverging from earlier proposals like the AirRail consortium’s dedicated line from Southern Cross.
Key figures in the announcement include Victorian Premier Ben Carroll and Prime Minister Anthony Albanese, who emphasized the project’s importance for unlocking rail capacity and connecting Melbourne’s west to the airport. Carroll, whose electorate includes Keilor East, framed the project as a pre-election priority, while Albanese highlighted its role in building Victoria’s future. ABC quotes Carroll describing the delays as 'deeply distressing' to the community, while 7NEWS and THEAGE focus on the economic and logistical benefits, including the expected 5200 daily passengers at Keilor East and 6600 hourly passengers on the airport rail line.
While all sources agree on the core details of stage two’s timeline and the 7.4-kilometre rail line, there are differences in emphasis. ABC highlights the unresolved timeline for the final connection to the airport, while 7NEWS and THEAGE focus on the project’s broader economic impact and the unresolved final stage. THEAGE provides additional financial details, noting the project’s budget has expanded to $12 billion and that the Tullamarine Freeway is projected to reach capacity by 2036. ABC also mentions earlier timelines of 2029 and 2033, which have since been revised, while THEAGE clarifies that the 2033 timeline was tentative and subject to uncertainty.
Despite the progress, significant challenges remain. THEAGE reports that a steering committee is still negotiating the final connection to Tullamarine, raising the possibility of further delays. ABC notes that the timeline for the rail line between Keilor East and the airport itself is yet to be finalised, while 7NEWS and THEAGE both mention that the final stage of the project lacks a clear completion date. The articles suggest that while stage two is advancing, the full airport rail link’s completion remains dependent on resolving outstanding issues, including compensation claims from Melbourne Airport and federal-state negotiations.
✓ Verified by 2+ sources
Key details reported by multiple sources:
- A new 7.4-kilometre rail line from Albion to Keilor East station will begin major construction in 2028, with Keilor East station due for completion by 2031.
- The project includes a 500-metre rail bridge over the Maribyrnong River.
- Stage one of the Melbourne Airport Rail project, the $4.1 billion Sunshine Superhub, is expected to be completed by 2031.
- Construction on stage two of the airport rail link will begin in coming weeks with site investigations and procurement, with community engagement and early designs starting next year.
- The Melbourne Airport rail link has been discussed since the 1960s, with delays spanning decades.
- The project was paused in 2023 due to disputes over the station location (underground vs. above ground) and a federal infrastructure review.
- Melbourne Airport agreed to an above-ground station in July 2024, allowing the project to progress.
- The Keilor East station is expected to serve 5200 passengers daily.
- The airport rail line is expected to handle 6600 passengers every hour.
- The project is a joint commitment by the federal and Victorian Labor governments, with a total budget of $12 billion.
- Construction on the Sunshine Superhub began in February 2023.
- The project includes a connection to the Metro Tunnel.
Points of Difference
Details reported by only one source:
- The Victorian government previously announced the airport rail line would run by 2029, then 2033, but has since gone quiet on a final completion date.
- The project has faced setbacks, including disputes over station location and arguments between the airport and state government over underground vs. above-ground construction.
- The timeline for a rail line between Keilor East and the airport itself is yet to be finalised.
- The community has been waiting for the Keilor East railway station for 62 years, with delays described as 'deeply distressing' by then-Mooney Valley mayor Pierce Tyson in 2023.
- The $12 billion project is expected to be completed in 2031, one year after stage one is ready.
- The final stage of the project, including an above-ground station at the airport precinct, remains without a clear completion date.
- Construction for the project was paused in 2023 after Melbourne Airport Rail became entangled in a federal infrastructure review.
- The airport rail line is expected to be used by 6600 passengers and airport workers every hour.
- The project’s final cost remains uncertain, with a 2022 budget of $11.5 billion and an estimated ceiling of up to $13 billion.
- Victoria has committed $5 billion, with the federal government contributing another $2 billion, bringing the total taxpayer funds to $12 billion.
- The project’s scope has expanded significantly through the $4 billion Sunshine Superhub program.
- The Tullamarine Freeway is projected to reach capacity by 2036 and become increasingly congested after that, with vehicle travel times set to double by 2056.
- The Andrews government opted to build the airport connection via Sunshine, with airport trains running through the CBD to the eastern suburbs via the Metro Tunnel.
- The project was a political quagmire in the 2020s, despite early works being underway and negotiations starting on contracts for major packages.
- The Allan government pushed out the timeline on airport rail in April 2023 due to a stalemate with Melbourne Airport over the station’s location.
- The federal government appointed a steering committee in March 2023 to resolve outstanding issues, including claims from the airport for compensation.
Where the reporting differs
Details that conflict, or appear in only some outlets:
- ABC states the Keilor East station is due for completion 'three years later' (implying 2031), while THEAGE explicitly states it will be completed by 2031, but does not mention a 'three years later' reference.
- ABC mentions a '500-metre rail bridge' without specifying its location, while 7NEWS and THEAGE clarify it is over the Maribyrnong River.
- ABC and 7NEWS both mention a 2029 and 2033 timeline for the airport rail line, but ABC states the government has 'gone quiet' on a final completion date, while THEAGE notes the 2033 timeline was tentative and subject to uncertainty.
- 7NEWS and THEAGE mention the project was paused in 2023, but ABC does not explicitly state a pause, only that there were delays and disputes.
- THEAGE notes the project was budgeted at $11.5 billion in 2022, while 7NEWS does not mention this specific figure.
Source Articles
Key station in Melbourne Airport rail plan to be built by 2031
A long-awaited train line to the Melbourne Airport is a step closer, with the state and federal governments announcing a timeline for completion of the nearby Keilor East station.
New Keilor East train station to drive Melbourne Airport rail link expansion
Its final completion date still remains unknown.
Carroll makes tracks in pre-election rush to build airport rail link
Trains will be running to Keilor East within five years, Premier Ben Carroll is promising, taking Victorians one step closer to a rail line all the way to Tullamarine airport.
More Politics stories
Australia’s Reserve Bank raises interest rates amid inflation crisis, economic slowdown risks
Greens leadership change after Larissa Waters' resignation due to health
Vietnamese authorities detain Australian activist and colleagues amid allegations of abduction and terrorism
Greens leader Larissa Waters steps down due to illness ahead of next election
Trump bans CNN, MS Now, Politico from White House, sparking legal battle
Alex Antic elected SA Liberal Party president amid factional tensions
Latest cross-verified stories
Pilot stabbing on Dubai-Tel Aviv flight sparks hijack fears, emergency landing in Saudi Arabia
Lachie Neale's AFL grand final suspension appeal and eventual clearance to play
RBA raises cash rate to 4.6%, highest since 2011, impacting mortgages and inflation
Manchester City found guilty of Premier League financial breaches in historic scandal
Former American Idol contestant Caleb Flynn convicted of murdering his wife Ashley Flynn
Tragic death of Hannah Camplin, partner of AFL premiership hero Mark Hutchings, after childbirth
Browse all stories from September 2026 in the archive.