Victoria’s Big Build royal commission investigates CFMEU’s influence and alleged corruption in 2022 projects

By Updated 9 November 20262 articles from 2 independent sources

Consensus Summary

Victoria’s Big Build royal commission is examining allegations of corruption and undue influence by the Construction, Forestry, Maritime, and Energy Union (CFMEU) over major infrastructure projects, with a central focus on the June 2022 stop-work at the Gap Road level crossing removal in Sunbury. Both the Guardian and ABC report that work halted on June 6, 2022, after CFMEU officials intervened, only resuming the following day after control of the site was transferred to the union. The hearings have revealed internal documents from contractor John Holland, including a 2017 memo describing the CFMEU’s ‘unprecedented access’ to government ministers and its growing influence over tender processes. The commission has also highlighted a pattern of union interference, such as the CFMEU officials entering the Gap Road site 29 times in January 2020, with some activity deemed unlawful.

The background to the royal commission’s investigation traces back to the CFMEU’s expanding role in Victoria’s political and industrial landscape. Internal emails from John Holland, cited by both outlets, show concerns dating back to 2017 about the union’s relationship with the Andrews Labor government, including fears that the CFMEU could shape government tenders. By 2021, the union was described as ‘emboldened’ and enjoying ‘a significant level of influence’ within the state government, a shift that contractors attributed to its success on major projects. The commission’s focus on the June 2022 meeting at Gap Road underscores how this influence allegedly translated into direct interference with construction work, including threats against subcontractors and coordinated stoppages.

Key figures in the hearings include Counsel Assisting Chris Young KC, who presented evidence of the CFMEU’s tactics, and Neil Thompson, the health and safety manager for the Rail Network Alliance, who described the union’s disruptive actions in detail. The Guardian reports that Thompson called police on June 6, 2022, after CFMEU officials blocked work, but Victoria Police took no action, citing occupational health and safety issues. Premier Ben Carroll addressed the hearings, denying knowledge of the CFMEU’s access to senior officials, while the opposition leader, Jess Wilson, criticized the government for funding legal representation for former premiers Jacinta Allan and Daniel Andrews. The ABC highlights Carroll’s denial and the union’s alleged threats, including a warning to subcontractors that they would be ‘smash[ed]’ if they continued working.

While both sources agree on the core events—such as the June 2022 stop-work and the CFMEU’s historical influence—they emphasize different aspects of the story. The Guardian provides more detail on the timeline of union interference, including the 29 site visits in January 2020 and the escalation of risks leading to the June 2022 meeting. It also includes the premier’s comments on legal representation and the opposition’s criticism, framing the hearings as part of a broader pattern of union-government collusion. The ABC, however, focuses more on the immediate threats and the financial impact of the stop-work, noting the $6 million cost overrun and the union’s alleged intimidation tactics, such as the ‘smash you’ warning. Neither outlet disputes the central facts, but their framing differs in scope and emphasis.

The royal commission’s hearings are set to continue until November 28, coinciding with the state election, as reported by the ABC. The Guardian notes that the commission is relying on witness memories of events from four years ago, given the lack of documentation about the June 2022 meeting. Both outlets suggest that the hearings will uncover further details about the CFMEU’s role in other Big Build projects, with the ABC mentioning ‘remarkably similar experiences’ from contractors on different sites. The unresolved question remains whether the commission will find sufficient evidence to substantiate allegations of corruption, particularly given the limited clarity around the pivotal June 2022 meeting and the union’s historical influence over government decisions.

✓ Verified by 2+ sources

Key details reported by multiple sources:

  • The royal commission hearings focus on the CFMEU’s involvement in the Gap Road level crossing removal project in Sunbury in June 2022, where work was stopped by union officials.
  • A June 2022 meeting between government officials and CFMEU officials was central to the commission’s hearings, though details of the meeting remain unclear.
  • CFMEU officials entered the Gap Road project’s eastern portal 29 times in January 2020, with some activity considered unlawful.
  • Work at the Gap Road site ceased on June 6, 2022, and resumed on June 7, 2022, after control was transferred to the CFMEU.
  • The CFMEU’s relationship with the Victorian government was described in a 2017 internal memo from John Holland as having ‘unprecedented access’ to ministers and stakeholders.
  • The royal commission has received more than 110,000 documents as part of its investigation.
  • The hearings began in November 2022, with a focus on events leading up to the June 2022 stop-work at Gap Road.

Points of Difference

Details reported by only one source:

The Guardian
  • The commission heard that 20 witnesses were compelled to appear during the November hearings, focusing on government officials’ actions during the June 2022 meeting.
  • A 13-minute meeting took place on June 6, 2022, followed by a subsequent meeting at the CFMEU, which resolved the issues, though details remain unclear.
  • The CFMEU was described as ‘emboldened by their success on major infrastructure projects’ in 2021, with ‘a significant level of influence within the state government’.
  • The premier, Ben Carroll, confirmed legal representation for two former premiers, Jacinta Allan and Daniel Andrews, was ‘supported by the state’ as in ‘other previous royal commissions’.
  • The opposition leader, Jess Wilson, criticized the taxpayer-funded legal representation for former premiers, stating it ‘doesn’t pass the pub test.’
  • A recording of a phone call between Neil Thompson (health and safety manager for the Rail Network Alliance) and WorkSafe on June 6 showed Thompson was unclear about how to proceed, with Victoria Police unable to intervene.
ABC News
  • Project costs at Gap Road blew out by an estimated $6 million due to the stop-work.
  • The royal commission hearings continue until November 28, days before the state election.
  • Premier Ben Carroll denied any knowledge of the CFMEU’s access to senior government officials during the hearings.
  • The commission heard that CFMEU officials threatened subcontractors, including a warning: ‘you guys better not turn up tonight otherwise we’ll smash you during the day.’
  • The hearings explored themes including allegations of threats of violence against subcontractors, with police and WorkSafe Victoria notified but taking no action.

Where the reporting differs

Details that conflict, or appear in only some outlets:

  • The Guardian states that the November hearings involved 20 witnesses compelled to appear, while the ABC does not mention this specific number of witnesses.
  • The Guardian notes that the CFMEU’s influence was described as ‘not seen in previous years and is unlikely to diminish’ in 2021, whereas the ABC focuses more on the immediate threats and access to ministers in 2017 and 2022.
  • The Guardian includes a reference to a ‘very high risk rating’ applied to the possibility of industrial action on Gap Road, which the ABC does not mention.

Source Articles

GUARDIAN

CFMEU ‘enjoy a significant level of influence’ over Victorian government, Big Build royal commission hears

Inquiry into allegations of corruption begins block of hearings focused on 2022 level crossing removal project Get our daily political email , free app or daily news podcast The royal commission into allegations of corruption on Victorian Big Build projects has heard a major construction company feared putting the Construction, Forestry and Maritime Employees Union (CFMEU) offside because of its close links to the Andrews Labor government. The first block of hearings under the commission into th

ABC

Victoria's Big Build inquiry hears CFMEU threatened to 'smash' subcontractor

Public hearings started with the events leading up to a stop-work at a Sunbury level crossing removal site in June 2022.

More Politics stories